Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH’s
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
According to PRINCE2, which statement about the Configuration Management Strategy for the
Outsourcing project is correct?

PrepAway - Latest Free Exam Questions & Answers

A.
Every project needs a Configuration Management Strategy, even if the organization has
existing configuration management standards, because every project has different circumstances.

B.
A separate Configuration Management Strategy will be required for each of the suppliers within
this project because each will have a different way of managing and storing products.

C.
A Configuration Management Strategy is unnecessary for this project because the MFH
document control process is documented. It is acceptable simply to reference this in the Quality
Management Strategy.