Which option is an appropriate Change Authority for the Outsourcing project?

While preparing the Configuration Management Strategy, the Project Manager considered the
options for change control. He decided to recommend a change budget of £250k, but was
undecided on the Change Authority to recommend.
Which option is an appropriate Change Authority for the Outsourcing project?

PrepAway - Latest Free Exam Questions & Answers

A.
The selected service provider to approve and implement all changes.

B.
Senior User(s) and Project Assurance representatives, within the limits of the recommended
change budget.

C.
The Director of Facilities and the Director of Information Technology to approve all changes.