It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO’s customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.

Which product should show that the staff photo sessions were disruptive to the Engineering
Department as they had been scheduled during peak work times without consultation with the
Engineering Manager?

PrepAway - Latest Free Exam Questions & Answers

A.
Follow-on action recommendations

B.
Lessons Report

C.
Project closure notification

D.
Risk Register