which of these products will require updating?

During stage 1 the level of performance expected from the service provider was changed.
After this change was agreed which of these products will require updating?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Brief because this is maintained throughout the project to reflect the customer’s quality
expectations.

B.
Project Product Description because this contains details of the expected performance of the
project’s products.

C.
Quality Management Strategy because this is where all of the customer’s quality expectations
of the project’s products should be documented.