Which project controls should be established for the Outsourcing project?

Which project controls should be established for the Outsourcing project?

PrepAway - Latest Free Exam Questions & Answers

A.
Highlight Reports to the Project Manager; Exception Reports to the Project Board when project
tolerances are forecast to be exceeded.

B.
Highlight Reports to the Project Board; Exception Reports to corporate management when
stage tolerances are forecast to be exceeded.

C.
Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or
project tolerances are forecast to be exceeded.