PrepAway - Latest Free Exam Questions & Answers

Which option provides an appropriate way for the Project Manager proceed?

While preparing the Quality Management Strategy, the Project Manager noticed that the corporate
quality management system does not specifically cover project management.
Which option provides an appropriate way for the Project Manager proceed?

PrepAway - Latest Free Exam Questions & Answers

A.
Record the development of a corporate quality management system for project management as
a prerequisite of the Project Plan.

B.
Proceed with the project without a Quality Management Strategy and adopt the selected

service provider’s standards in stage 4.

C.
Seek relevant organizational standards, then facilitate a workshop to discuss the Quality
Management Strategy with Project Assurance.


Leave a Reply