complete the transition of the services to the selected service provider.

HOTSPOT
Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).

3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
At the end of stage 3, the service provider will be selected and the contract awarded. During stage
4, the Account Manager for the selected service provider will work with the Project Manager to
complete the transition of the services to the selected service provider.

PrepAway - Latest Free Exam Questions & Answers

Answer:

Explanation:

One Comment on “complete the transition of the services to the selected service provider.

  1. BASEL H M ALHARTANY says:

    For question 5
    The team manager informs through checkpoint report or raise an issue
    The job of project manager is create exception report and post project board with it.. so it should be false true.