PrepAway - Latest Free Exam Questions & Answers

Which 2 statements should be recorded under the Roles and responsibilities heading?

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract

for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients’ work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor’s calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
Which 2 statements should be recorded under the Roles and responsibilities heading?

PrepAway - Latest Free Exam Questions & Answers

A.
Each risk will be assigned a risk owner.

B.
Risks exceeding the agreed project risk tolerance will be reported to the Project Board.

C.
Risk tolerances are allocated to each stage by the Project Manager.

D.
Project Assurance will ensure that project risks are identified, assessed and controlled
according to the agreed risk management procedure.

E.
An external consultant is to facilitate a risk identification workshop.


Leave a Reply