Which product should show that the photos could be used for other promotional material for the company?

It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO’s customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Which product should show that the photos could be used for other promotional material for the
company?

PrepAway - Latest Free Exam Questions & Answers

A.
Benefits Review Plan

B.
Lessons Log

C.
Exception Report

D.
End Project Report