PrepAway - Latest Free Exam Questions & Answers

Which one of the following is the only thing that the r…

Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?

PrepAway - Latest Free Exam Questions & Answers

A.
Project document updates

B.
Risk register updates

C.
Change requests

D.
Risk register


Leave a Reply