During which of the following processes, probability and impact matrix is prepared?

PrepAway - Latest Free Exam Questions & Answers

A.
Plan Risk Responses

B.
Perform Quantitative Risk Analysis

C.
Perform Qualitative Risk Analysis

D.
Monitoring and Control Risks