what term?

A high-profile, high-priority project within your organization is being created. Management wants you to pay special attention to the project risks and do all that you can to ensure that all of the risks are identified early in the project. Management has to ensure that this project succeeds.
Management’s risk aversion in this project is associated with what term?

PrepAway - Latest Free Exam Questions & Answers

A.
Utility function

B.
Risk conscience

C.
Quantitative risk analysis

D.
Risk mitigation