PrepAway - Latest Free Exam Questions & Answers

Where should you document the proposed responses and th…

You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk management plan

B.
Stakeholder management strategy

C.
Risk register

D.
Lessons learned documentation


Leave a Reply