PrepAway - Latest Free Exam Questions & Answers

What document is Frank and the NHH Project team creatin…

Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team.
What document is Frank and the NHH Project team creating in this scenario?

PrepAway - Latest Free Exam Questions & Answers

A.
Project management plan

B.
Resource management plan

C.
Risk management plan

D.
Project plan


Leave a Reply