What will you reply to your team member?

You work as a project manager for BlueWell Inc. You with your team are using a method or a (technical) process that conceives the risks even if all theoretically possible safety measures would be applied. One of your team member wants to know that what is a residual risk. What will you reply to your team member?

PrepAway - Latest Free Exam Questions & Answers

A.
It is a risk that remains because no risk response is taken.

B.
It is a risk that remains after planned risk responses are taken.

C.
It is a risk that can not be addressed by a risk response.

D.
It is a risk that will remain no matter what type of risk response is offered.