PrepAway - Latest Free Exam Questions & Answers

what other documentation will need to be updated as an …

Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?

PrepAway - Latest Free Exam Questions & Answers

A.
Lessons learned

B.
Scope statement

C.
Risk Breakdown Structure

D.
Technical documentation


Leave a Reply