You are the project manager of the CUL project in your organization. You and the project team are assessing the risk events and creating a probability and impact matrix for the identified risks.
Which one of the following statements best describes the requirements for the data type used in qualitative risk

analysis?

PrepAway - Latest Free Exam Questions & Answers

A.
A qualitative risk analysis requires fast and simple data to complete the analysis.

B.
A qualitative risk analysis requires accurate and unbiased data if it is to be credible.

C.
A qualitative risk analysis required unbiased stakeholders with biased risk tolerances.

D.
A qualitative risk analysis encourages biased data to reveal risk tolerances.