What is the formula for the schedule variance?

Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?

PrepAway - Latest Free Exam Questions & Answers

A.
SV=EV-PV

B.
SV=EV/AC

C.
SV=PV-EV

D.
SV=EV/PV