PrepAway - Latest Free Exam Questions & Answers

Who is correct in this scenario?

Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is familiar with the technology that the risk is

affecting and proposes to Nancy a solution to the risk event. Nancy tells Bob that she has noted his response, but the risk really needs to pass through the quantitative risk analysis process before creating responses. Bob disagrees and ensures Nancy that his response is most appropriate for the identified risk. Who is correct in this scenario?

PrepAway - Latest Free Exam Questions & Answers

A.
Bob is correct. Bob is familiar with the technology and the risk event so his response should be
implemented.

B.
Nancy is correct. Because Nancy is the project manager she can determine the correct procedures for risk
analysis and risk responses. In addition, she has noted the risk response that Bob recommends.

C.
Nancy is correct. All risks of significant probability and impact should pass the quantitative risk analysis
process before risk responses are created.

D.
Bob is correct. Not all risk events have to pass the quantitative risk analysis process to develop effective
risk responses.


Leave a Reply