PrepAway - Latest Free Exam Questions & Answers

what additional information can you associate with the …

You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk schedule

B.
Risk potential responses

C.
Risk cost

D.
Risk owner


Leave a Reply