PrepAway - Latest Free Exam Questions & Answers

Which type of risk response is this?

A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?

PrepAway - Latest Free Exam Questions & Answers

A.
Avoidance

B.
Mitigation

C.
Exploit

D.
Transference


Leave a Reply