You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the quantitative risk analysis process?

PrepAway - Latest Free Exam Questions & Answers

A.
Probability of reaching project objectives

B.
Risk contingency reserve

C.
Risk response

D.
Risk register updates