PrepAway - Latest Free Exam Questions & Answers

What individual should respond to the risk with the pre…

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Diane

B.
Risk owner

C.
Subject matter expert

D.
Project sponsor


Leave a Reply