Where can Mark determine the priority of a risk given i…

Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk response plan

B.
Project sponsor

C.
Risk management plan

D.
Look-up table