Which of the following would measure a project’s validity?
A. Risk analysis
B. Strategic alignment
C. Resource allocation
D. Gantt chart
2 Comments on “Which of the following would measure a project’s validity?”
Reneesays:
ATTN: The correct answer is B. Admin, please fix.
Thanks!
0
0
Edsays:
Alignment to the strategic plan can also be included within the business case, and it should describe how the project and its outcomes will align to the organization’s overall strategic plan. If the reason for the project doesn’t support the strategic plan, there’s really no reason to undertake the project
ATTN: The correct answer is B. Admin, please fix.
Thanks!
0
0
Alignment to the strategic plan can also be included within the business case, and it should describe how the project and its outcomes will align to the organization’s overall strategic plan. If the reason for the project doesn’t support the strategic plan, there’s really no reason to undertake the project