which of the following items are required for the pre-project setup?

In order to prepare a project charter, which of the following items are required for the pre-project
setup?

PrepAway - Latest Free Exam Questions & Answers

A.
Assumptions, constraints, project deliverables, and all resources required for the project.

B.
Client name, client project manager, organization project manager, and a complete project
budget.

C.
Direction from team members, development methodology, and staff requirements.

D.
Business need, assumptions, constraints, project deliverables, and staff requirements.