Which of the following methods is the project manager demonstrating?

A project manager is performing activity sequencing. The project manager is only using start to
finish dependencies. Dummy activities are being utilized to define all logical relationships. Which
of the following methods is the project manager demonstrating?

PrepAway - Latest Free Exam Questions & Answers

A.
Precedence Diagramming Method (PDM)

B.
Critical Chain Method (CCM)

C.
Arrow Diagramming Method (ADM)

D.
Critical Path Method (CPM)

One Comment on “Which of the following methods is the project manager demonstrating?

  1. Michael McNeil says:

    The precedence diagram method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.

    Critical tasks, noncritical tasks, and slack time
    Shows the relationship of the tasks to each other
    Allows for what-if, worst-case, best-case and most likely scenario

    Key elements include determining predecessors and defining attributes such as

    early start date
    late start date
    early finish date
    late finish date
    duration
    WBS reference