A project manager is completing a project schedule network diagram using dummy activities to show all logical relationships. Which of the following tools is the project manager using?
A. ADM
B. WBS
C. AON
D. PDM
4 Comments on “Which of the following tools is the project manager using?”
Trolsays:
Is this dump still valid?
0
0
Tommy Picklessays:
If you take a pk0-003 test, likely. They have a pk0-004 test and that may contain a lot of different questions, but likely based on the same material so a pk0-003 book would probably help you.
0
0
Mark Slatersays:
I took PK0-003 today (NOT the educational version JK0-017) and not a single one of the questions from this dump was on the test. Passed with a 770 primarily due to studying. It’s worth noting that a handful of questions did come from .V2 that is posted on aiotestking.
MAKE SURE YOU STUDY, DO NOT RELY ON AIOTESTKING FOR PROJECT+
0
0
Sparkylifesays:
Besides, part of that new 115Q PK0-004 dumps are available here:
Is this dump still valid?
0
0
If you take a pk0-003 test, likely. They have a pk0-004 test and that may contain a lot of different questions, but likely based on the same material so a pk0-003 book would probably help you.
0
0
I took PK0-003 today (NOT the educational version JK0-017) and not a single one of the questions from this dump was on the test. Passed with a 770 primarily due to studying. It’s worth noting that a handful of questions did come from .V2 that is posted on aiotestking.
MAKE SURE YOU STUDY, DO NOT RELY ON AIOTESTKING FOR PROJECT+
0
0
Besides, part of that new 115Q PK0-004 dumps are available here:
https://drive.google.com/open?id=0B-ob6L_QjGLpWmFpamxGZTNmX0U
Best Regards!
0
0