PrepAway - Latest Free Exam Questions & Answers

Which of the following would BEST mitigate the risk of injury to those team members, without affecting the app

During execution, a project manager of a construction project requires certain project team
members to work outdoors, atop tall buildings. Which of the following would BEST mitigate the risk
of injury to those team members, without affecting the approved project schedule?

PrepAway - Latest Free Exam Questions & Answers

A.
Ensure that project team members do not work in very windy weather.

B.
Ensure that project team members are furnished with slip-resistant boots.

C.
Ensure that project team members are trained in injury response.

D.
Ensure that project team members are covered by applicable insurance.

One Comment on “Which of the following would BEST mitigate the risk of injury to those team members, without affecting the app

  1. Michael McNeil says:

    Admin: Correct answer is B

    Insurances does not reduce risk of injury and though ensuring team members do not work in windy weather reduces risk of injury, it does affect schedule.




    0



    0

Leave a Reply