    Schedule Performance Indicator (SPI)

    Schedule Performance Indicator is an index showing the efficiency of the time utilized on the project. Schedule Performance Indicator can be calculated using the following formula:

    SPI = Earned Value (EV) / Planned Value (PV)

    OR

    SPI = BCWP / BCWS

    The formula mentioned above gives the efficiency of the project team in utilizing the time allocated for the project.

    SPI value above 1 indicates project team is very efficient in utilizing the time allocated to the project.

    SPI value below 1 indicates project team is less efficient in utilizing the time allocated to the project.