Which of the following will MOST likely be affected by these circumstances?

A project manager is managing the delivery of a project awarded under a fixed-cost contract. The
project cost was poorly planned and underestimated, but the projects overall scope and deadline
cannot change. Failure to deliver the project is not an option. Which of the following will MOST
likely be affected by these circumstances?

PrepAway - Latest Free Exam Questions & Answers

A.
Earned Value (EV)

B.
Quality

C.
Change management

D.
Resource leveling

Explanation: