Which of the following methods would a project manager use to estimate the construction cost of a 2,000 square

Which of the following methods would a project manager use to estimate the construction cost of a
2,000 square foot home when given the cost per

PrepAway - Latest Free Exam Questions & Answers

A.
Parametric estimating

B.
Analogous estimating

C.
Top-down estimating

D.
Bottom-up estimating