Which of the following will be impacted?

A project manager was called into the office of the Chief Information Officer (CIO) and informed

that the resource budget for the company has been reduced by 10%. The CIO expects that the
project must be completed on time. Which of the following will be impacted?

PrepAway - Latest Free Exam Questions & Answers

A.
Project scope will be impacted.

B.
Quality will be impacted.

C.
WBS will be impacted.

D.
SOW will be impacted.