Which of the following would be the BEST response for the project manager?

A project manager has analyzed work performance information and identified alarming variances
in the project deliverable. Which of the following would be the BEST response for the project
manager?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform a qualitative risk assessment.

B.
Speak with the project sponsor about possible solutions.

C.
Approve a change request to correct the actions.

D.
Recommend corrective actions.