PrepAway - Latest Free Exam Questions & Answers

Which of the following should be the NEXT

A key stakeholder has asked the project manager to complete the project a week earlier than
expected. To accomplish this objective, the project manager will have to ask the project team to
work overtime, which will increase the cost of the project. Which of the following should be the
NEXT

PrepAway - Latest Free Exam Questions & Answers

A.
Ask the key stakeholder for more funding for the project.

B.
Ask the project team to work overtime to finish the project.

C.
Obtain an approved change control document before changing the project schedule.

D.
Agree to complete the project using the new schedule.


Leave a Reply