Which of the following would be the BEST way to deal with the manager’s repeated request?

A project manager is in a projectized organization managing a particular project. A department
manager has repeatedly requested a change to the scope of the project which was previously
denied. The project is currently behind schedule. Which of the following would be the BEST way to
deal with the manager’s repeated request?

PrepAway - Latest Free Exam Questions & Answers

A.
Request the manager fill out a formal request for the change and file it with the project
management office.

B.
Have a team member meet with the manager so the project can stay on schedule.

C.
Ask the project sponsor to respond to the department manager.

D.
Implement the change as requested by the manager and inform the project sponsor.