All of the following should be detailed in the communications management plan EXCEPT:

All of the following should be detailed in the communications management plan EXCEPT:

PrepAway - Latest Free Exam Questions & Answers

A.
the person responsible for communicating the information.

B.
team member roles and responsibilities.

C.
team member roles and responsibilities.

D.
frequency of project team communications.

One Comment on “All of the following should be detailed in the communications management plan EXCEPT:

  1. Michael McNeil says:

    Admin: Please fix. Answer should be B & C

    In project management, communication management must address the following questions:[2]http://en.wikipedia.org/w/index.php?title=Communications_management&action=info

    What information needs to flow in and out of the project?
    Who needs what information?
    When is the information needed?
    What is the format of the information?
    Who will be responsible for transmitting and providing the information?