The project manager crashes a project that is behind schedule and under-budget. Which of the
following will be the intended result?

A.
The project will be behind schedule and over-budget.
B.
The project will be on schedule but over-budget.
C.
The project will be on schedule and on-budget.
D.
The project will be behind schedule and on-budget.
The intended result should that the project will be on schedule and on-budget.
0
0
The correct answer is C.
0
0
Since Crashing adds resources, how can you remain on-budget?
0
0
Because it is CURRENTLY under-budget, so it can afford to have new resources added.
0
0