A project manager is performing activity duration estimation. This project will have conditional decisions. Which of the following tools would be the BEST to use?
A. GERT
B. Gantt chart
C. PERT
D. EVM
2 Comments on “Which of the following tools would be the BEST to use?”
Gantt charts are used to gauge a project schedule
http://en.wikipedia.org/wiki/Gantt_chart
0
0
It is PERT, hence the reference to ‘conditional decisions’ in the question. Ie: dependencies
http://www.inc.com/encyclopedia/program-evaluation-and-review-technique-pert.html