Which of the following should the project manager do to gather this information?

A project manager needs to determine how much it will cost for a third party to complete certain
deliverables and the steps they will take to complete those deliverables. Which of the following
should the project manager do to gather this information?

PrepAway - Latest Free Exam Questions & Answers

A.
Issue a RFQ

B.
Issue an RFP

C.
Create a WBS

D.
Develop a SOW

Explanation: