Which of the following should the project manager do to compensate for this unmet expectation?

At a project milestone meeting, the project sponsor asked about a deliverable that is not on the
project plan. Which of the following should the project manager do to compensate for this unmet
expectation?

PrepAway - Latest Free Exam Questions & Answers

A.
Review the scope with the vendor.

B.
Review the scope with the customer

C.
Review the scope with the team.

D.
Review the scope with the sponsor.