A hurricane is forecasted near the corporations call center. The project manager has arranged for
a redundant call center in another location to accept calls if the corporate call center is unable to
receive calls. Which of the following risk responses is the project manager using?

A.
Avoidance
B.
Acceptance
C.
Mitigation
D.
Transference
Admin the correct answer is C.
0
0
Michael is correct. The answer is C. Transference is when the risk is transferred to another party (such as a vendor) not transferring the functionality of a project deliverable. Mitigation is when you reduce the impact of the risk, which is what the questions is asking.