Get 50% Discount on All Your Purchases at PrepAway.com - Latest Exam Questions This is ONE TIME OFFER 50% Enter your email address to receive your 50% off dicount code: A confirmation link will be sent to this email address to verify your login. GET YOUR DISCOUNT CODE * We value your privacy. We will not rent or sell your email address.
50% Enter your email address to receive your 50% off dicount code: A confirmation link will be sent to this email address to verify your login. GET YOUR DISCOUNT CODE * We value your privacy. We will not rent or sell your email address.
SPECIAL OFFER: GET 50% OFF 50% Use Discount Code: BRIEF50 A confirmation link was sent to your e-mail. Please check your mailbox for a message from support@prepaway.com and follow the directions. Shop Now
50% Use Discount Code: BRIEF50 A confirmation link was sent to your e-mail. Please check your mailbox for a message from support@prepaway.com and follow the directions. Shop Now
Which of the following represents the ETC of this project? seenagapeApril 17, 2014 In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project? A.$150,000 B.$300,000 C.$450,000 D.$600,000 Show Answer
Michael McNeil says: June 29, 2014 at 2:50 am 1/3 of the Miles completed, which means 1/3 of the BAC is expended, which means that the answer should be D. Estimate To Complete (ETC) Estimate To Complete (ETC) is the estimated cost required to complete the remainder of the project. Estimate To Complete (ETC) is calculated and applied when the past estimating assumptions become invalid and a need for fresh estimates arises. ETC is used to compute the Estimation At Completion (EAC). Budget At Completion (BAC) Budget At Completion (BAC) is the total budget allocated to the project. Budget At Completion (BAC) is generally plotted over time. Say like periods of reporting (Monthly, Weekly, etc.) BAC is used to compute the Estimate At Completion (EAC), explained in next section. BAC is also used to compute the TCPI and TSPI. Estimate To Complete (ETC) Estimate To Complete (ETC) is the estimated cost required to complete the remainder of the project. Estimate To Complete (ETC) is calculated and applied when the past estimating assumptions become invalid and a need for fresh estimates arises. ETC is used to compute the Estimation At Completion (EAC). 0 0
1/3 of the Miles completed, which means 1/3 of the BAC is expended, which means that the answer should be D.
Estimate To Complete (ETC)
Estimate To Complete (ETC) is the estimated cost required to complete the remainder of the project.
Estimate To Complete (ETC) is calculated and applied when the past estimating assumptions become invalid and a need for fresh estimates arises.
ETC is used to compute the Estimation At Completion (EAC).
Budget At Completion (BAC)
Budget At Completion (BAC) is the total budget allocated to the project.
Budget At Completion (BAC) is generally plotted over time. Say like periods of reporting (Monthly, Weekly, etc.)
BAC is used to compute the Estimate At Completion (EAC), explained in next section.
BAC is also used to compute the TCPI and TSPI.
Estimate To Complete (ETC)
Estimate To Complete (ETC) is the estimated cost required to complete the remainder of the project.
Estimate To Complete (ETC) is calculated and applied when the past estimating assumptions become invalid and a need for fresh estimates arises.
ETC is used to compute the Estimation At Completion (EAC).
0
0
1/3 of $900,000 is $300,000.
0
0