PrepAway - Latest Free Exam Questions & Answers

Which of the following is the FIRST action the project manager should take?

During a status meeting, a team member informs the project manager of a possible risk. Which of
the following is the FIRST action the project manager should take?

PrepAway - Latest Free Exam Questions & Answers

A.
Record the risk in the risk register.

B.
Work with the team to develop a risk response.

C.
Perform an initial prioritization of the risk.

D.
Determine the probability and impact of the risk.

2 Comments on “Which of the following is the FIRST action the project manager should take?


Leave a Reply