The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to
date. The project is currently 50 percent complete. Which of the following is the earned value
(EV)?

A.
$35,624.00
B.
$59,373.33
C.
$71,243.00
D.
$35,497.60
Can someone explain how A. is the correct answer? If CPI = EV/AC, then 1.2 * 71248 = EV, which does not equal A.
0
0
The Answer is D, however there is a typo in that the first 3 should be an 8. Steve is correct with the formula and the answer is $85,497.60 (D).
0
0
BTW, part of that new 115Q PK0-004 dumps are available here:
https://drive.google.com/open?id=0B-ob6L_QjGLpWmFpamxGZTNmX0U
Best Regards!
0
0