Which of the following is a benefit of the work breakdown structure (WBS)?
A.
It will provide a detailed budget for the stakeholders.
B.
Items not included in the project objectives can be added to the WBS for flexibility.
C.
it will ensure that scope will not occur.
D.
Contains all activities required to complete the project.
