A project manager seeks to implement a change control system. Which of the following elements
are essential for this system to be effective? (Select THREE).

A.
Change request form
B.
Approval mechanism
C.
Pareto chart
D.
Impact analysis
E.
Earned Value (EV) analysis
Admin: Please fix. The correct answer would be A, B, & D
0
0
AIOTK, Funny how elated you are to delete my comments, yet you just leave this Michael dude’s demands for different answers published without any problem. You don’t just change answers because someone says so. And you don’t just say “Fix this. Answer should be…” without citations or proof of any kind. WTF.
0
0
Whoa.
0
0
There are several aspects to an effective change management system. We’ll look at each of these elements throughout this section. The change management process includes the following:
Change request forms (and other documentation)
Change request log
Analysis of the impacts of change
Change control board (CCB)
Coordination and communication with appropriate stakeholders
Updating the affected project-planning documents