The change control board has just approved a request to modify the sampling technique for a
project. Which of the following documents would the project manager update?

A.
Risk management plan
B.
Quality management plan
C.
Communication management plan
D.
Scope management plan
Admin: Please fix, the answer is D
0
0
The correct answer is B. Quality management uses statistical (or other types of) sampling. Scope Management uses Change Control, but no sampling.