The project manager has been informed that the project team cannot procure any more materials
until a new purchase order has been received. The project manager should record this information
in which of the following documents?

A.
Risk response plan
B.
Communications plan
C.
Issues log
D.
Change control log
Clearly this is an Issue.
0
0
Correct answer is C.