Which of the following describes the LOWEST level of a work breakdown structure (WBS)?
A. Technical specifications
B. Project performance reports
C. Work packages
D. Functional specifications
4 Comments on “Which of the following describes the LOWEST level of a work breakdown structure (WBS)?”
Jonsays:
The answer is C) Work packages.
0
0
Johnsays:
Work packages are the lowest level of the WBS and are pieces of work that are specifically assigned to one person or one team of people to be completed.
0
0
MrIntelsays:
The correct answer is C, work packages.
0
0
Alan Smithsays:
BTW, part of the new 115Q PK0-004 dumps are available here:
The answer is C) Work packages.
0
0
Work packages are the lowest level of the WBS and are pieces of work that are specifically assigned to one person or one team of people to be completed.
0
0
The correct answer is C, work packages.